A “nearly impossible” pedestrian path
The Fuller Warren Bridge’s new shared use path.
The long, strange journey of the Fuller Warren Bridge bike and pedestrian path dates all the way back to December 2013, when Florida Department of Transportation District 2 quietly announced a public hearing for its Tentative Five-Year Work Program. The announcement didn’t make clear that this included a massive, $136 million proposal affecting Jacksonville’s busiest highway interchange. The project involved widening the Fuller Warren Bridge, which carries I-95 over the St. Johns River, from four lanes to eight, and would also reconfigure the flyover ramp from I-10 to Roosevelt Boulevard.
The announcement immediately drew questions and pushback, as it seemed to come out of nowhere. FDOT hadn’t previously discussed a need to widen the Fuller Warren, and in fact had just wrapped up major improvements to the interstates in this area. Critics questioned the high price tag and lack of community outreach, as well as the impact the project would have – as proposed, the expansion would have threatened homes and offices in Riverside and Mixontown, as well as the popular Riverside Arts Market. One common critique was that despite its cost and scope, the project didn’t include any accommodations for pedestrians and cyclists.
James Bennett, the urban transportation development manager for FDOT District 2, said the department would work with locals on some design changes, but on the question of the bike and pedestrian element, he put it bluntly: such an addition was “nearly impossible.” According to FDOT, no federal highway bridges had bike and pedestrian crossings, and the Fuller Warren would be no different. “This is an interstate,” Bennett said. “There is not going to be sidewalks or bike paths put across this bridge on an interstate.”
The power of public action
The shared use path under construction in September 2018. (Ennis Davis, AICP)
The Jaxson team was among the first to write about the Fuller Warren expansion and push back on some of FDOT’s statements. Writing on his earlier website Metro Jacksonville, Jaxson cofounder Ennis Davis explained the forthcoming changes and the impacts it would have on surrounding neighborhoods. He also refuted FDOT’s claim that a bike and pedestrian walkway was nearly impossible. Not only was it perfectly possible, at that time such walkways already existed on dozens of interstate highway bridges, including in various other segments of I-95.
Further public feedback came quickly through December. Riverside Avondale Preservation joined the chorus, as did many citizens and some members of Jacksonville City Council. “You know this project is going to be scrutinized,” council member Robin Lumb told FDOT at a conference. “The credibility of FDOT has taken some hits… I’m sorry to put you in the hot seat here, but you guys have some real catching up to do.”
FDOT agreed to accept public input, but the department initially doubled down on their refusal to include a multi-use path, going so far as to launch a website arguing that this type of path was illegal under Florida law.
A bike lane or highway shoulder vs. a physically separated path. (The Jaxson)
We refuted this point as well, noting that the law actually stipulated that bike lanes unseparated from the road weren’t allowed on federal highways, although even there, there were some exceptions. But with the Fuller Warren, citizens weren’t calling for bike lanes, they wanted physically separated paths. This is an important distinction. Not only were physically-separated paths kosher under Florida law, there were already a number of examples across Florida that FDOT itself had built.
“If the expansion of the Fuller Warren Bridge ends up not including a bicycle/pedestrian connection, it will not be because it can’t legally happen,” Davis wrote. “Rather, it will be because FDOT does not want to include a multimodal option, even if it would help improve mobility, mulitmodal safety, and the area’s quality of life.”
As it turned out, public action and community engagement worked. FDOT considered the feedback and went back to the drawing board. On April 1, 2014, nine City Council members issued a statement explaining that FDOT had agreed to a number of conditions for the new project to minimize its negative impacts and maximize its benefits. In August 2014, FDOT released a new plan with many significant changes that reduced the footprint of the project and avoided demolishing more homes and offices. Importantly, the “nearly impossible” bike and pedestrian bridge was included.
A new asset is born
The Fuller Warren Bridge shared use path alongside the highway. (WJCT News)
This being Jacksonville, both the Fuller Warren widening and the completion of the multi-use path experienced a number of delays. The project was initially expected to be completed in summer 2020. But finally, on April 6, 2023, FDOT opened the 4,654-foot-long, 12-foot-wide Fuller Warren Bridge Shared Use Path.
With much fanfare surrounding the opening, without a doubt FDOT will eventually win awards for working with the community to bring this project – now a critical piece of the proposed Emerald Trail system – to fruition. However, the real story and lesson with this project went unnoticed by the masses and overlooked in the ribbon-cutting ceremonies. That story, the most inspiring element of this project’s completion, begins and ends with the local Jacksonville community. A decade ago, concerned bloggers and residents found a way to work together and demand a better transportation solution from their represented leaders. As a result, the Fuller Warren Bridge shared use path is a real life example of the saying, “where there is a will, there is a way.”
Editorial by Bill Delaney and Ennis Davis, AICP. Contact Bill at wdelaney@moderncities.com. Contact Ennis at edavis@moderncities.com.