GRTC Pulse

(wbur.org)

  • City: Richmond, VA
  • Technology: Bus Rapid Transit
  • Year Completed: June 24, 2018
  • Length: 6.8 miles
  • Construction Costs: $65 million
  • Construction Costs per mile: $9.6 million

El Paso Streetcar

(Downtown El Paso)

  • City: El Paso, TX
  • Technology: Heritage Streetcar (Refurbished PCC Streetcars)
  • Year Completed: November 9, 2018
  • Length: 4.8 miles
  • Construction Costs: $97 million
  • Construction Costs per mile: $20 million

Oklahoma City Streetcar

(Wikipedia)

  • City: Oklahoma City, OK
  • Technology: Modern Streetcar (Brooksville Liberty)
  • Year Completed: December 14, 2018
  • Length: 4.8 miles
  • Construction Costs: $136 million
  • Construction Costs per mile: $28 million

Cincinnati Bell Connector

(City of Cincinnati)

  • City: Cincinnati, OH
  • Technology: Modern Streetcar (CAF Urbos 3)
  • Year Completed: September 9, 2016
  • Length: 3.6 miles
  • Construction Costs: $150 million
  • Construction Costs per mile: $42 million